“DESIGN OF A GENERAL PLAN FOR THE ORGANIZATION OF TRAFFIC (GPOD)” IN THE TOWN OF SILISTRA
IMPOSER
Municipality of Silistra
“DEVELOPMENT OF A GENERAL PLAN FOR THE ORGANIZATION OF TRAFFIC IN THE CITY OF PAVLIKENI”
IMPOSER
Pavlikeni municipality
“DEVELOPMENT OF A GENERAL TRAFFIC ORGANIZATION PLAN (GPOD) OF THE CITY OF ROMAN”
IMPOSER
Roman municipality
“PREPARATION OF A GENERAL PLAN FOR THE ORGANIZATION OF TRAFFIC IN THE CITY OF RUSE”
IMPOSER
Municipality of Ruse
DESIGN AND AUTHOR SUPERVISION OF ROAD RECONSTRUCTION BETWEEN THE VILLAGES OF KALOYANOVETS AND LOVETS BY KM. 0+000 TO KM. 5+459
IMPOSER
Stara Zagora Municipality
ROAD III- 609 (KAZANLAK – O.P. SLIVEN) – RADUNTSI – KRUSTES – PLACHKOVTI – TRIAVNA – TSAREVA LIVADA – DRYANOVO – GOSTILITSA – BURIA -(III-406), SECTION FROM KM 0+000 TO KM 23+500, WITH TOTAL LENGTH 23,500 KM
IMPOSER
OPU Stara Zagora
“DEVELOPMENT OF A GENERAL TRAFFIC ORGANIZATION PLAN (GPOD) OF THE CITY OF ROMAN”
IMPOSER
OPU Gabrovo
Development of a technical project for carrying out a major repair of a site: “Road III-301 from km 0+000 to km 11+730”
IMPOSER
OPU Pleven
Development of conceptual project and navel-parcel plan/plan for amendment of street regulation for northern road junction “Trapezitsa” At km 101+000 on road I-5 “Ruse-Byala-Vel. Tarnovo” (Connection with road III-514)
IMPOSER
Agency Road Infrastructure
General plan for the organization of traffic in the city of Veliko Tarnovo
IMPOSER
Veliko Tarnovo municipality
General plan for the organization of traffic (GPOD)” in the city of Mezdra
IMPOSER
Municipality of Mezdra
Installation of traffic lights at the intersection of “Simeon Veliki” St. and “Hadji Dimitar” St. – Silistra city
IMPOSER
Municipality of Silistra
Construction of a connecting pedestrian and bicycle path
“Zheleznik” quarter with Thrace University (running parallel to
road III-6602 (Bogomilovo – Stara Zagora – Stara Zagora mineral baths – Pastrovo), in the section from km. 1+960 to km 3+534, to the left in the direction of growth km.)
IMPOSER
Stara Zagora Municipality
Reconstruction of a flat culvert (bridge facility) in the village of Mihailovo at km 11+721 on the SZR 1190 road (Borovo village – Mihailovo village)
IMPOSER:
Stara Zagora Municipality
Preparation of PUP and technical projects for the modernization of the railway section Elin Pelin – Ihtiman
IMPOSER:
State Railway Infrastructure National Company (NRI), Bulgaria Implementation period: January 2015 – December 2016 Project goal:
Increasing the design speed to 160 km/h, modernization by subsystems and achieving interoperability
Scope of the project:
• Preparation of a technical project for the modernization of the railway section Elin Pelin – Ihtiman;
• Coordination and approval by the competent authorities of the technical projects for modernization in accordance with the requirements of the current Bulgarian legislation;
• Registration of technical passports for the existing building stock, stations and facilities within the scope of the project;
• Creation of Detailed Development Plans;
• Preparation of documents for starting expropriation procedures and changing the status of the land;
• Preparation of technical specifications for construction.
In its position as a leading partner in the DZZD ELIH consortium, TRANSGEO performed the overall management, contract administration and design.
Highlights of the project:
• Optimization of the existing route for 160 km/h;
• Part of the designed facilities are railway spurs in the area of Pobit Kamak with a total length of 648 m and two tunnels with lengths of 970 m and 6,680 m. Between the tunnels, two one-way bridges over the Gabra River with ballastless superstructure are designed;
• The traction power supply in tunnels 1 and 2 is designed with a contact rail;
• A project has been prepared for the reconstruction of the reception building of the Elin Pelin station and the adjacent infrastructure – parking lot, footbridge;
IMPOSER:
State Railway Infrastructure National Company (NRI), Bulgaria Implementation period:: July 2014 – 2023 Project goal:
Development of railway infrastructure in accordance with European standards and transport policy; Optimization of the existing infrastructure related to the safety of the railway network; Improving the operational railway process;
Scope of the project:
TRANSGEO participated in the development of the project as a leading partner in the DZZD “Trakia Consult” consortium and performed the overall management and administration of the contract.
The contract was implemented in 3 stages, carried out in full according to the requirements of the technical specification of the Contracting Authority: The scope of the contract includes the following projects and individual items:
Project 1 – ”Development of the Plovdiv railway interchange”;Project 2 – ”Preparation for the construction of sections on the railway line Plovdiv – Burgas”, including the activities under the following separate positions:
• Item 1 – Construction of an optical cable along the Plovdiv – Burgas line;
• Item 2 – Removal of crossings and construction of overpasses/underpasses for the railway section Plovdiv – Burgas;
• Item 3 – Construction of signaling systems on the railway line Plovdiv – Burgas (ETCS level 1, version 2.3.0d);
• Item 4 – Rehabilitation of the Skutare – Orizovo railway section;
• Item 5 – Modernization of the railway section Orizovo – Mihailovo;
• Item 6 – Modernization of the railway section Yambol – Zimnitsa, near Zavoy station;
• Item 7 – Reconstruction of the shooting development at the Zimnitsa station;
• Pos. 8 – Rehabilitation of the contact network in the interstation Zimnitsa – Tserkovski, incl. Straldza railway station;
• Item 9 – Rehabilitation of the railway section Straldzha – Tserkovski;
• Item 10 – Repair of buildings and facilities in the Karnobat railway station complex;
• Pos. 11 – Construction of a protected forest belt in the Chernograd – Aytos intersection;
• Item 12 – Implementation of station centralizations in the Karnobat – Burgas section.
Highlights of the project
• Construction of signaling systems – 18 pcs. route computer centralizations, dispatch centralization and train traffic control system – ETCS level 1;
• Construction of an optical cable network and systems for telecommunications in the section Plovdiv – Burgas;
• Removal of crossings and construction of overpasses/underpasses for a conflict-free crossing with the railway infrastructure within the scope of the Plovdiv – Burgas section;
• Modernization of the existing infrastructure for railway sections: railway junction Plovdiv, Skutare – Orizovo;
• Doubling and increasing the design speed (160 km/h) for the railway sections Orizovo – Mihailovo and Yambol – Zimnitsa at Zavoy station;
• Reconstruction of the shooting development at Zimnitsa station;
• Repair of buildings and facilities in the Karnobat railway station complex;